Robot Cabling Go-Live Gate

A supervised pilot where a robot cables one rack per shift (54 copper management and 36 front-end fiber connections) for 15 shifts. When can the robot work without a tech watching? Simulated data.

Can the robot work unsupervised?

Yes, from shift 16. After shift 15 the GO streak reaches 10 with no blocking note. Copper reached 10 in a row first, after shift 14.

Shift gateOne square per shift; 15 racks, 90 connections each
10GO shifts in a row
needs 10, no blocking note
UNSUPERVISED
Note triageClaude tags 30 tech notes, 3 runs each
28-29of 30 notes passed per run
0 critical failures
GO
Keyword taggerNo model; the same notes and gate. Why it fails
22of 30 notes passed
5 critical failures
NO-GO
Weekly updateClaude writes the customer update from each week's fact sheet
3of 3 weekly updates sent
0 critical failures
GO
GO, or passed every runPARTIAL Failed a runNO-GO, or a critical failure Select a square to open its report.

Stage timeline, shift by shift

Blocking notes from Claude triage (recorded run, notes gate GO). Select a shift to see every connection.

Showing the latest shifts. Scroll back for shift 1 and the row labels.

Shift gateBlocking noteStreaksGO, and copper onlyCopper stageFiber stageCopper first passFiber first passRobot interventionsCustomer misses10 in a row1NG00503372NG005235313NG00523524NG00523625P01533436GO12543517GO23533618GO345436019GO455336010GO565436011GO675335212GO785436013GO895336114GO9105435115GO10115436016nextSupervisedUnsupervisedSupervisedUnsup.
GO streakCopper streak SupervisedUnsupervised Underlined: below the GO line (53 copper, 35 fiber)

How a shift is graded

Each shift is graded connection by connection:

  • Right port
  • Latched
  • Link up
  • Label
  • Clean fiber end face
  • Fiber receive power
  • Cycle time
  • Nobody stepping in
  • No live cable disturbed

GO

53 of 54 copper and 35 of 36 fiber connections right the first time, with no live cable (one already linked up, on this rack or a neighbor) disturbed.

Copper first

A fiber-only miss is PARTIAL and lets copper go first. The copper streak keeps going through a PARTIAL shift, so copper reaches 10 in a row first and can go unsupervised while fiber stays supervised.

Unsupervised

Ten GO shifts in a row, with no tech note that blocks unsupervised work, moves the robot to unsupervised shifts.

Misses the customer's network team fixed are reported but not counted against the robot. Built on golive-gate.

Every shift

ShiftRackGate Copper first passFiber first passRobot interventions Blocking note GO streakCustomer missesCopper streakNext shift
Shift 1R01NO-GO50 of 5433 of 367yes00supervised
Shift 2R02NO-GO52 of 5435 of 363010supervised
Shift 3R03NO-GO52 of 5435 of 362yes00supervised
Shift 4R04NO-GO52 of 5436 of 362yes00supervised
Shift 5R05PARTIAL53 of 5434 of 36301supervised
Shift 6R06GO54 of 5435 of 36112supervised
Shift 7R07GO53 of 5436 of 36123supervised
Shift 8R08GO54 of 5436 of 360314supervised
Shift 9R09GO53 of 5436 of 36045supervised
Shift 10R10GO54 of 5436 of 36056supervised
Shift 11R11GO53 of 5435 of 36267supervised
Shift 12R12GO54 of 5436 of 36078supervised
Shift 13R13GO53 of 5436 of 36189supervised
Shift 14R14GO54 of 5435 of 361910copper unsupervised, fiber supervised
Shift 15R15GO54 of 5436 of 3601011unsupervised

Weekly update to the customer

Claude writes each week's update from that week's fact sheet; a rule check holds any number not in the sheet, and a Claude judge holds any unsupported claim. Gate: GO (details).

Robot cabling pilot, week 1 (shifts 1-5): supervised next week

Week 1 covered shifts 1-5. The robot cabled 5 racks and 450 connections. First-pass results were 259 of 270 on copper and 173 of 180 on fiber, for 96.0% overall. There were 17 interventions, or 3.8 per 100 connections, and 1 miss was customer-caused. We recorded 1 live disturbance and 3 safety stops. Against the gate, the week had 0 go shifts, 1 partial and 4 no-go, and 3 shifts carried a blocking note. The go streak stands at 0, and 10 consecutive go shifts are needed before unsupervised work. The robot will work supervised next week because the gate has not been met.

Gate: sent (all checks passed)

Robot cabling pilot, week 2 (shifts 6-10): supervised next week

This week the robot cabled 5 racks, 450 connections. First-pass success was 268 of 270 on copper and 179 of 180 on fiber, 99.3 percent overall. There were 2 interventions, 0.4 per 100 connections, and 1 miss was customer-caused. There were 0 live disturbances and 0 safety stops. All 5 shifts passed the gate as go, with 0 partial, 0 no-go, and 0 shifts carrying a blocking note. The go streak stands at 5 against the 10 required to move to unsupervised work. Because the streak has not reached 10, the robot stays supervised next week.

Gate: sent (all checks passed)

Week 3 cabling pilot update: robot moves to unsupervised work next week

Week 3 covered shifts 11-15. The robot cabled 5 racks and 450 connections. First-pass results were 268 of 270 copper and 178 of 180 fiber, for 99.1 percent overall. There were 4 interventions (0.9 per 100 connections), 0 customer-caused misses, 0 live disturbances and 1 safety stop. All 5 shifts were gate go, with 0 partial, 0 no-go and 0 shifts carrying a blocking note. The go streak ended the week at 10, which meets the 10 required by the gate. The robot will therefore work unsupervised next week.

Gate: sent (all checks passed)

Tech note triage

30 constructed tech notes, 3 runs each. Claude tags each note (failure mode, owner, safety, blocks unsupervised work, needs review) and writes a one-line summary; rules grade the tags and a Claude judge grades the summary. Gate: GO (every note and verdict).

90triage calls
1.9 smean per note, $0.0082 each
$0.43judge, in total
GroupPassed every check (notes x 3 runs)
robot30 of 30
site26 of 27
customer12 of 12
safety12 of 12
unclear6 of 9

The same gate blocks a keyword tagger: NO-GO. It misses safety notes that never say “e-stop” (see why).